Well after our "community stacking" event on Sunday where Deb, Tom & Boom, Sangeetha & Chris, Mark & Alex and Bonita helped, the crew of Clark Construction finished the stacking of the lower level walls on Monday and Tuesday. So on Wednesday they were ready for the first big pour.

I took the day off and came in the morning to help get the penetrations ready that I had marked the previous evening. And at a quarter past twelve the pumper showed up - unfortunately not the nice guy we had for the footings on Thursday but a rather "different" individual (they couldn't get the nice guy again)...

Then, at 12:55 PM, the concrete trucks showed up (Tony had ordered them for 1 PM and from what I understand last week they were late showing up for the pouring of the footing). Tony created some motivation by letting us know that all the concrete trucks are lined up at the bottom of the hill... A few minutes later, while Lyndon Lee, the ICF form distributor from Mabel, Lyndon Clark and Paul Hynes were still laying hands on last minute preparations, Tony was pumping away starting in the 9" wall between the studio and the storage room. All walls were filled about half-way with the first pour.

After that, Lyndon hooked up his Vibrator backpack and together Lyndon and Tony worked the concrete - I think they looked like Ghostbuster chasing away the airbubble demons ;-). The Vibrator that Lyndon is holding helps the concrete to settle all the way done. Actually the scientific way to test whether the concrete is all the way down to the bottom is to take a short piece of 2x4 and bang it, carefully and with the flat side, against the wall. If it sounds hollow, there is no concrete in.


Radio Licht 'n Stein

Comments: Post a Comment

<< Home

This page is powered by Blogger. Isn't yours?